Rwanda

Ericsson / MTN & Airtel Account

  • 2G/3G RBS Engineering, implementation and Troubleshooting.
  • Sites Survey Audit for Managing Services Project.
  • Modernization Project for 2G (G9 and G18), 3G (U9 and U21) and 4G Networks including civil works, new RBS sites and swapping existent RBS equipment.
  • Conducting SRS
  • Site Installation: 2G (G9 and G18) installation activities, activation & cutover & Troubleshooting ERS / RUS.
  • Transmission: Complete Network Swap including Engineering, Implementation, testing and troubleshooting.
  • High Capacity SDH long haul radio system implementation, testing and troubleshooting.
  • TCU installation and configuration.
  • G1800 TRX Expansion.
  • IP RAN/ ROUTER INSTALLATION AND CONFIGURATION
  • RBS swap (2K to 6K).
  • Materials Dismantling and transportation to warehouse
  • Consultancy: Delegating high Qualified engineers to Ericsson for supervising the overall work done by ASPS.
  • Resources supply to Ericsson (RAN IM, Optimization and planning engineers, drive test team)
  • Handling Logistics and Supply